6 costly problems, and how to avoid them
Let’s be straight with each other. After 70 years of experience across three generations and hundreds of projects, we’ve seen a lot of planning mistakes at Emesh. Some are small and easy to fix. Others are expensive and hold up the whole project.
Here’s the interesting part: most of these mistakes repeat themselves, the same problems project after project. The difference between a project that runs smoothly and one that doesn’t usually isn’t the quality of the work. It’s the early planning. Here are the six most common mistakes and how to avoid them.
The difference between a smooth project and a troubled one usually isn’t the quality of the work. It’s the early planning.
Mistake #1: “The carpenter will figure it out”
- The problem: A plan that shows “oak cabinet” with no detail on the shade, panel thickness, hardware type or grain direction.
- What happens in practice: The carpenter has to make decisions in the architect’s place, which sometimes leads to a result that’s different from the original vision.
- The solution: Detailed shop drawings, where every detail is documented and every decision is made before production begins.
- From our experience: Sometimes an architect asks for a “matte” finish, but after we show the different levels of matte at Emesh, they discover they wanted something completely different. Better to find that out before production.
Mistake #2: Ignoring how it gets installed
- The problem: Designing a stunning bookcase 3 meters (10 ft) tall when the doorway into the room is only 80 cm (about 31 in) wide.
- What happens in practice: The bookcase has to be broken down into smaller units on site, which can hurt the look and drive up costs.
- The solution: Plan the logistics up front: how the pieces get into the space, the assembly order and the size of the elevator.
- Questions worth asking:
- How wide are the openings on the way to the space?
- Is there an elevator, and how big is it?
- Are there narrow stairs along the way?
- Can the elements be brought in as a single unit?
Mistake #3: Not accounting for material movement
- The problem: Wood is a “breathing” material that expands with humidity and shrinks when it’s dry. Without proper planning, you get cracks or warping.
- Classic examples: Doors that stick in humid weather, tabletops that crack because of a joint that’s too rigid, or panels that pull loose.
- The solution: Planned gaps and joints that allow movement, especially when wood is combined with rigid materials like metal or glass.
Mistake #4: Choosing hardware too late
- The problem: The “build first, pick hinges later” approach.
- What happens in practice: You find out the hinges don’t suit the construction, the door is too heavy, or there’s simply no physical room for the hinge you wanted.
- The solution: Define the hardware during the design phase, since the type of hinges and slides directly affects the cabinet’s construction and the depth of the drawers.
- What to define up front: Hinge type and opening range, the load capacity of the drawer slides, and opening mechanisms (push-to-open or handles).
Mistake #5: Poor coordination between trades
- The problem: The carpenter and the metal fabricator work from separate plans, and at assembly the dimensions don’t match.
- Why it happens: There’s no single, unified document that every trade works from.
- The solution: Joint shop drawings that capture every joint between materials and every critical dimension. At Emesh, we set up coordination meetings with the glass fabricators, metal fabricators and electricians before production even starts. In most cases we manage the entire process ourselves, so the client gets the finished product directly from us without having to deal with the other trades.
Mistake #6: Neglecting future maintenance
- The problem: Designing stunning features, like built-in lighting, that require taking apart half a cabinet just to change a bulb.
- More examples: Mechanisms that can’t be reached for repair, or fixed shelves that can’t be moved when your needs change.
- The solution: Design with the long term in mind: access to the lighting drivers, hinges that can be adjusted and finishes that can be refreshed.
- Tip from the field: Moshe, our CEO and owner, always reviews plans with architects with the future in mind: if the client calls in a few years, how will we get in and repair a particular component?
How do you avoid these mistakes?
The simple answer is to bring the woodshop in during the early stages of design. Getting Emesh involved early makes it possible to:
- Spot problems before they become expensive.
- Adapt the design to advanced production methods.
- Plan installation and logistics in advance.
- Choose the right materials and hardware.
This doesn’t mean giving up on the design idea. It means finding the most sound, stable technical way to make it happen.
Checklist before starting a millwork project
- ☐ Are there detailed shop drawings?
- ☐ Has the hardware been selected and specified?
- ☐ Is the installation method clear to everyone?
- ☐ Have we checked that the pieces physically fit into the space?
- ☐ Has everything been coordinated with the other trades?
- ☐ Have future maintenance needs been taken into account?
- ☐ Have the material combinations been worked out technically?
If the answer to every question is “yes,” your project is on track to run smoothly.